Housing Construction Programme

housing units june 2021 update

SCHEMES COMPLETED

Pinewood Rapid Build

20 rapid build units consisting of 12 x 3 bed houses and 8 x 2 bed houses have been completed.

Wellview Rapid Builds

20 rapid build units consisting of 12 x 3 bed houses and 8 x 2 bed houses have been completed.

Racecourse Common

74 units consisting of 9 x 4 bed houses, 36 x 3 bed houses and 29 x 2 bed houses (including specially adapted units) have been completed.

Ballyboughal

6 units consisting of 1 x 4 bed semi-detached unit, 2 x 3 bed semi-detached units, 3 x 2 bed semi-detached units and 2 refurbished 3 bed bungalows (specially adapted) have been completed.

Avondale Rapid Build

Construction commenced on the 26th February 2018 of 42 units consisting of 6 x 4 bed houses, 18 x 3 bed houses and 18 x 2 bed houses in Avondale, Mulhuddart, Dublin 15 and they have been completed.

Church Road Rapid Build

Construction commenced in July 2018 of 22 units consisting of 4 x 4 bed units, 6 x 3 bed units, 10 x 2 bed units and 2 x 1 bed units and they have been completed.

Castlelands

Construction commenced on the 14th February 2017 of 24 units consisting of 10 x 3 bed 2 storey houses, 10 x 2 bed 2 storey houses, 2 x 2 bed apartments and 2 x 1 bed apartments and they have been completed.

Pinewood Community Centre

This was a redevelopment of the disused community centre at Pinewood Green Avenue, Balbriggan, Co. Dublin.  The construction consisted of 2 x 1 bed semi-detached bungalows and both have been completed.

Rivermeade

2 x 3 bed houses at Rivermeade, St. Margaret’s have been completed.

Rowlestown

Construction commenced on the 11th June 2018 of 26 units consisting of 2 x 4 bed, 2 storey semi-detached houses; 10 x 3 bed, 2 storey semi-detached houses; 10 x 2 bed, single storey semi-detached houses; and 4 x 2 bed, single storey detached houses. They have been completed.

Rathbeale Road

Construction commenced in October 2018 of 24 units comprising of 3 x 4 bed houses, 11 x 3 bed houses, 6 x 2 bed houses and 4 x 2 bed apartments. They have been completed.

 

SCHEMES ON SITE

Wellview Infill Site

Construction commenced in November 2020 of 20 units comprising of 7 x 2 bed 2 storey dwellings, 7 x 3 bed 2 storey dwellings and 6 x 4 bed 2 storey dwellings in Wellview Estate, Mulhuddart, Dublin 15.

Planning Ref: PARTXI/006/18 – Planning application and all relevant document can be searched here: https://planning.agileapplications.ie/fingal/search-applications/

Dun Emer, Lusk

Construction commenced in May 2021 of 51 units in Dun Emer, Lusk.  The 51 units will comprise of 39 Affordable houses and 12 Social Housing units.  The 12 social housing units (including 5 x Part V units) all comprise of 4 bed houses.  Four of these units will be designated for special needs.

Planning Ref: FS5/010/21 - Planning application and all relevant document can be searched here: https://planning.agileapplications.ie/fingal/search-applications/

Cappaghfinn

Construction commenced in June 2021 of 69 units at Cappaghfinn consisting of 10 x 1 bed units, 26 x 2 bed units, 25 x 3 bed units, 8 x 4 bed units.

Planning Ref: PARTXI/008/19 - Planning application and all relevant document can be searched here: https://planning.agileapplications.ie/fingal/search-applications/

 

SCHEMES AT TENDER STAGE

Tuckett’s Lane, Howth

Proposed development of 4 x 2 bed units and 4 x 1 bed units. This is at Tender Stage.

Planning Ref: PARTXI/004/18 - Planning application and all relevant document can be searched here: https://planning.agileapplications.ie/fingal/search-applications/

Churchfields Phase 2B 

Proposed development of 67 dwellings including 6 x 1 bed bungalow units, 17 x 2 bed units, 34 x 3 bed units and 10 x 4 bed units. This is at Tender Stage.

Planning Ref: PARTXI/010/19 - Planning application and all relevant document can be searched here: https://planning.agileapplications.ie/fingal/search-applications/

Outlands-Rathbeale Road

Proposed development of 11 Apartment Units mixed with 4 x 1 bed/2-person, 2 x 2 bed/3-person, 2 x 2 bed/4 person and 3 x 3 bed/six person apartments. This is at Tender Stage.

Planning Ref: PARTXI/003/19 - Planning application and all relevant document can be searched here: https://planning.agileapplications.ie/fingal/search-applications/

Katie Hunt Site Church Road Lusk

Proposed development for 5 x 2 bed/3 person dwellings at Church Road Lusk Co Dublin, formerly known as Katie Hunt’s cottage. Part 8 granted at Full Council Meeting on 14th September 2020.

Planning Ref: PARTXI/003/20 - Planning application and all relevant document can be searched here: https://planning.agileapplications.ie/fingal/search-applications/

Leonards Garage at Barrack Lane/Dublin Road Junction Lusk

Proposed development of 4 x 2 bed single storey dwellings, 5 x 2 bed duplex dwellings at first floor level with stairs/lift/external walkway access and 1 live in artist 2 bed unit. Part 8 granted at the Full Council Meeting on 9th November 2020.

Planning Ref: PARTXI/004/20 - Planning application and all relevant document can be searched here: https://planning.agileapplications.ie/fingal/search-applications/

 

SCHEMES WITH PART 8 GRANTED

Infill Site beside 169 Clonsilla Rd Dublin 15

Proposed construction of a 2 bedroom semi-detached two storey dwelling to the side of the existing dwelling (no. 169 Clonsilla Road). Part 8 granted at the Full Council Meeting on 9th November 2020.

Planning Ref: PARTXI/002/20 - Planning application and all relevant document can be searched here: https://planning.agileapplications.ie/fingal/search-applications/

Hayestown, Rush, Co Dublin

Proposed development of 62 units in Hayestown, Rush, Co. Dublin.  The 62 units will comprise of 50 Affordable housing units and 12 Social Housing units.  Part 8 granted at the Full Council Meeting on 12th April 2021.

Planning Ref: PARTXI/005/20 - Planning application and all relevant document can be searched here: https://planning.agileapplications.ie/fingal/search-applications/

A new social housing development at Rolestown is under construction.