Swords Works Update
R132 Connectivity Project
The R132 Connectivity Project, which broke ground in April 2026, is broken into four phases from north of Pinnock Hill roundabout to Bostik Junction (North of Estuary roundabout). These works will improve the current transport infrastructure along this 3km route and facilitate works for the upcoming Metrolink project.
18th September
Works are progressing well along Phase One Bostik Junction to Estuary Roundabout. To facilitate progress and minimise traffic disruption, surfacing night works will commence on 21.09.2026 to 24.09.26 on Estuary Road, Estuary Junction and R125.
Bostik Junction section showing Walking Cycling lane and footpath
Bostik Junction crossing near completion
Ongoing work on the Northbound section of the R132 – Walking / Cycling lane