Housing Construction Programme

Please see the Housing Construction Programme below 

Housing Construction Programme

 

Overall Unit Numbers

Development Name

Status

20 units

Pinewood Rapid Build

Completed

20 units

Wellview Rapid Build

Completed

74 units

Racecourse Common

Completed

8 units

Ballyboughal

Completed

24 units

Castlelands

Completed

42 units

Avondale Rapid Build

On Site

22 units

Church Road Rapid Build

On Site

20 units

Rolestown

On Site

2 units

Pinewood Community Centre

On Site

2 units

Rivermeade

On Site

24 units

Rathbeale Road

On Site

24 units

Wellview Infill sites

Planning

8 units

Tuckett’s Lane

Planning

6 units

Rolestown Drive

Planning

 

 

SCHEMES COMPLETED

Pinewood Rapid Build

20 rapidly built units have been completed consisting of 12 x 3-bed houses and 8 x 2-bed houses

Wellview Rapid Builds

20 x 2 storey houses consisting of 12 x 3-bed houses and 8 x 2-bed houses have been completed.

Racecourse Common

74 units consisting of 9 x 4-bed houses, 36 x 3-bed houses and 29 x 2-bed houses. (Including specially adapted units) have been completed.

Ballyboughal

Construction commenced on 8th January 2018 of 8 units. It consists of 6 new builds – 1 x 4-bed semi-detached unit, 2 x 3-bed semi-detached units, 3 x 2-bed semi-detached units and 2 refurbished existing properties – 2 x 3-bed bungalows. (Specially adapted bungalows x2)

Castlelands

24 units consisting of 10 x 3-bed, 2 storey houses, 10 x 2-bed, 2 storey houses, 2 x 2-bed apartments and 2 x 1-bed apartments have been completed.

 

 

SCHEMES ON SITE

Avondale Rapid Build

Construction commenced on 42 units on 26th February 2018 consisting of 6 x 4-bed houses, 18 x 3-bed houses and 18 x 2-bed houses in Avondale, Mulhuddart, Dublin 15.

Church Road Rapid Build

Construction commenced on 22 units in July 2018 consisting of 4 x 4-bed units, 6 x 3-bed units, 10 x 2-bed units and 2 x 1 bed units.

Rolestown

Construction commenced on 11th June 2018 of 20 units consisting of 2 x 4-bed, 2 storey semi-detached houses, 10 x 3-bed, 2 storey semi-detached houses, 4 x 2-bed, single storey semi –detached houses, 4 x 2-bed, single storey detached houses.

Pinewood Community Centre

The redevelopment of the disused community centre at Pinewood Green Avenue, Balbriggan, Co. Dublin.  The proposal consists of 2 x 1-bed semi-detached bungalows. Contractor on site

Rathbeale Road

Construction  commencing October 2018 of 24 units comprising of 3 x 4-bed houses, 11 x 3-bed houses, 6 x 2-bed houses and 4 x 2 bed apartments.

Rivermeade

Contractor on site. The proposal is for 2 x 3-bed houses at Rivermeade, St. Margarets, Co. Dublin.

 

SCHEMES AT TENDER STAGE

Wellview Infill sites

Proposed development of 20 units at various sites within the current Wellview Estate, Mulhuddart, Dublin 15. Planning was granted at the Council meeting  Monday 8th April 2019. The design team are currently preparing tender documents.

Tuckett’s Lane

The proposal is for 4 x 2-bed units and 4 x 1-bed units.   Planning was granted at the Council meeting  Monday 8th April 2019. The design team are currently preparing tender documents.

Rolestown Drive

The proposal is for 6 x 2-bed semi-detached bungalows. Planning was granted at the Council meeting  Monday 8th April 2019.